Which data could be used as approved data for a major repair?

Prepare for the FAA Inspection Authorization Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get exam-ready efficiently!

Multiple Choice

Which data could be used as approved data for a major repair?

Explanation:
Major repairs must be performed in accordance with approved data. Approved data means information that has been reviewed and authorized by the FAA or by an FAA-approved design authority, such as an STC, PMA, or the design data tied to a type certificate. Data developed for and incorporated in a supplemental type certificate is FAA-approved design data that specifies exactly what needs to be done for the repair or alteration, making it valid for use in a major repair. The other sources don’t provide FAA-approved design data. Approval by an IA alone doesn’t create approved data for the repair. Data approved by the operator isn’t FAA-approved data and isn’t acceptable for major repairs. A manufacturer’s external memo by itself isn’t automatically FAA-approved design data unless it has been incorporated into an FAA-approved program (like an STC, PMA, or AD). So the STC-based data is the valid source for an approved major repair.

Major repairs must be performed in accordance with approved data. Approved data means information that has been reviewed and authorized by the FAA or by an FAA-approved design authority, such as an STC, PMA, or the design data tied to a type certificate. Data developed for and incorporated in a supplemental type certificate is FAA-approved design data that specifies exactly what needs to be done for the repair or alteration, making it valid for use in a major repair.

The other sources don’t provide FAA-approved design data. Approval by an IA alone doesn’t create approved data for the repair. Data approved by the operator isn’t FAA-approved data and isn’t acceptable for major repairs. A manufacturer’s external memo by itself isn’t automatically FAA-approved design data unless it has been incorporated into an FAA-approved program (like an STC, PMA, or AD). So the STC-based data is the valid source for an approved major repair.